A quotation is an invitation, not evidence. This scoring method turns a shortlist into a comparison you can defend to a board.
1. The eight dimensions that separate factories from catalogues
| Dimension | Weight | What to request |
|---|---|---|
| Safety and certification route | 25% | Calculation pack, EN 13814 / ASTM F2291 / GB 8408 mapping, CE or regional approvals |
| Factory and engineering capability | 20% | Factory visit, pre-assembly record, welding and material certificates, named engineers |
| Delivered references | 15% | Projects of the same height and market, with owner contact where possible |
| Scope completeness | 15% | Foundations, installation, training, commissioning and documentation clearly listed |
| Delivery and installation program | 10% | Production, freight, erection and commissioning schedule with milestones |
| Total cost of ownership | 10% | Spare parts, energy, inspection and maintenance plan over the design life |
| After-sales and local support | 5% | Response time, spare parts lead time, remote diagnostics, training scope |
Weights are a starting point; raise safety and references for public-facing landmarks, and raise cost for a seasonal attraction with a short payback horizon.
2. How to score each dimension
Scoring sequence
Normalise the scope
List the same deliverable set for every bidder before scoring, so one price is not cheaper simply because it excludes the foundation.
Score evidence, not promises
A claim becomes a score only when there is a document, a photo or a visit behind it. Unverifiable claims score zero.
Weight by project type
A park wheel weights throughput and delivery; a landmark weights safety, references and financing.
Run a site or factory visit
Verify fabrication is real: the pre-assembly record, the weld procedures and the test bay. A reseller cannot show these.
3. Red flags that should remove a bidder
- A price that excludes foundations, installation or the safety file without saying so
- No calculation pack or no named structural engineer for the design review
- No recent pre-assembly photos or test records for the model being quoted
- Vague references that cannot be visited or contacted
- A delivery date promised before the production, freight and installation times are added
4. Turning the score into a contract
The framework only protects you if its outputs are written into the agreement. Make the safety file a deliverable with its own payment milestone, tie the pre-shipment and commissioning tests to the payment schedule, and list the spare parts, training days and inspection intervals in the scope. A supplier that resists documenting these items is revealing more than any score can.
5. What a defensible decision memo contains
- The normalised scope every bidder was scored against
- The weighted scorecard with the evidence behind each score
- Factory-visit notes and the pre-assembly record reviewed
- The contract clauses mapped from the highest-weighted dimensions
- The reason a losing bidder failed, recorded in one documented line
6. The scoring traps that quietly distort a result
- Recency bias: weighting the most memorable presentation over the document record
- Low-price anchoring: letting a headline number override missing scope
- Brochure language: scoring adjectives rather than certificates and photos
- Scope drift: comparing wheels of different height or cabin spec as if equivalent
- Vendor-led weighting: accepting a supplier's weights instead of your project's
Evaluation FAQ
Can I use this framework without visiting the factory?
You can use it to shortlist, but the factory visit is the single highest-information step. If travel is not possible, request a live video walk-through of the workshop and the current pre-assembly, plus the record structure for a recent delivered wheel.
How many bidders should I score?
Three to five, after normalising the scope. More bidders than that usually means the scope was not defined clearly enough to compare.